Windermere’s Construction Update for May!

Hello and welcome to the construction update for May 2021! 

We’d like to begin this update with the advice that the Windermere Sales Gallery is closed until next Friday the fourth of June. This is in direct response to the latest update from the Victorian government enforcing the snap, seven-day lockdown. 

We hope that our community at large is staying home where possible and staying safe. The gallery will be deep cleaned and sanitised, and we look forward to welcoming you back on site as soon as the lockdown is lifted. 

Today, the Windermere team are proud to deliver to you the construction updates directly from the team on the ground!

Stages 1 – 8

  • Stages one through eight are titled.

Stages 1 – 8 Landscaping

The landscaping works for stages one through eight are forecasted to be completed by late June 2021.

Earthworks have been undertaken, in addition to weed spraying. Plants and grass are ready for installation, subject to the availability of topsoil.

Stage 9 & 10

  • Civil construction works for stages nine and ten are highly progressed, with all services installed.

  • Currently, the contractor is pouring concrete for the laneways and finalising the top layer of asphalt roads.

  • Once the laneways and roads are complete, the project team will seek Government approvals prior to lodgement of titles for registration.

  • The current registration forecast for both stages is July 2021.

Stage 15 – 16

  • All civil construction works are completed in Stages fifteen & sixteen.
  • We are currently seeking our final approvals from relevant Government Authorities prior to the lodgement of the required documentation to the title’s office.
  • Both stages are forecasted to title in early June 2021.
  • Civil construction in Stages fifteen & sixteen is highly progressed with the majority of items being completed.

Feature Fencing

  • The fencing contractor has commenced onsite to complete feature fencing, including all corner fencing. Stages 1-6 are completed. Stages 7 & 8 will commence shortly, followed by Stages 15 & 16.

Wetland Section 1

The landscape contractor is progressing works on-site.

This includes the installation of exercise equipment, soil preparation, concrete works (retaining walls), and artwork.

We’re excited for the trees and grass that are scheduled to be planted in June this year. The wetland plants are currently being contract grown and are scheduled to be installed in September 2021.

Thank you for following along the journey with us as the community forms from the ground up!