Construction update for September 2021!

Welcome to the Windermere construction update for September!

Over the past month, Windermere has seen some great construction progress here in Mambourin! Both stages nine and ten have been registered with the titles registration office. We have also made quite substantial progress with our landscaping works.

That being said, we are not immune to the recent two-week mandatory construction shutdown. These restrictions are likely to hamper works on site, and we may see some minor delays with roads and intersections, as well as potential delays with stages eleven and twelve.

Stages 8a, 9 and 10:

  • These stages at Windermere have now been registered with the land titles office.

Ison Road Intersection:

Windermere is currently constructing over 1km of Ison Road. This will include two intersections (Ison Road and Plane Avenue) and link the existing subdivision to stages eleven, twelve, fifteen and sixteen.

To date, earthworks, drainage and sub-grade preparation have been completed. All on-site works for Ison Road and Ison Road intersections are forecasted to be completed in early 2022.

Stages 11 and 12:

To date, earthworks, drainage, and sub-grade preparation have been completed. On-site works for stages eleven and twelve are also forecasted to be completed early next year, with titles following shortly after.

Corner Feature Fencing:

Windermere’s corner feature fencing has been completed in Stage fifteen, with Stage sixteen to resume once construction activity can recommence onsite. Stage sixteen is scheduled to be completed this month..

Landscaping, Greens Road, Stages 1 – 8 and Wetlands:

Landscaping works have been completed on stages one through four along Greens Road with trees and roll-on turf installed.

Stages five through eight have already had trees installed. Roll-on turf will be installed once construction can recommence on-site.

Waterway planting is occurring in Section one of the waterway that is adjacent to stages one and two. The wetland is scheduled to be completed by the end of the year.

Adjacent to stage nine, section Two of the waterway will commence works by the end of the year and be completed by mid-2022.

Thank you for following along our construction journey. We look forward to providing you monthly updates as we build the Windermere community from the ground up. The Windermere team are still available to you seven days a week, from 11 am through 5 pm. Please reach out to us on 1300 008 555 if you have any questions 🍃